Below is information on current and future road construction within the City.
|
Project
|
Start Date
|
Completion Date
|
Alternate Routes
|
|
11800 So Riverton Improvement Projects, Phase 3
Three part project to include: the addition of curb/gutter/sidewalk across the frontages of developed properties; sidewalk, property, and storm drain tie-in’s, and intersection improvements at 3600 West and 11800 South.
See Purchasing Web Page for Tabulation Awards
Lane Reduction’s Expected
|
July 2010
|
Sept, 2010
|
|
|
RDA Beautification Project Redwood Road
Roadway Completed; Landscaping to be completed in July 2010
Project includes the addition of curb/gutter/sidewalk across the frontages of properties; storm drain tie-in’s; asphalt and property tie-ins; Extensive landscape beatification.
See Purchasing Web Page for Tabulation Awards
|
April, 2010
|
August, 2010
|
2700 West &
1300 West
|
|
Street Light Retrofit
Project Complete
|
May 2010
|
July 2010
|
|
|
Public Works Wash Bay
Project Complete
|
May 2010
|
June 2010
|
|
|
11800 (2240 West -Redwood) Roadway Improvement Project
Project Complete
|
March, 2010
|
July, 2010
|
|
|
Overlay (4 Streets)
Doreen, Chartwell, 1830 West, Brindie Way
Project Complete
|
June 2010
|
June 2010
|
|
|
Micro Surface (6 Areas)
Project Complete
|
May 2010
|
June 2010
|
|
|
Slurry Seal (6 Areas)
Project Complete
|
May 2010
|
June 2010
|
|
|
ADA Ramps- Doreen Drive & 1830 West
Project Complete
|
April 2010
|
May 2010
|
|
|
ADA Ramps- Chartwell Area & Brindy Way
Project Complete
|
April, 2010
|
May, 2010
|
|
|
2010 Crack Seal Project (Micro-surface, Slurry Seal, and Overlay Area’s)
Project Complete
|
April, 2010
|
April, 2010
|
|
|
|
|
|
|
|
11800 (2700-2240 West) Roadway Improvement Project
Project Complete
|
April, 2009
|
September, 2009
|
11400 So & 12600 So
|
|
1300 West Riverbend Roadway Improvement
Project Complete
|
July, 2009
|
August, 2009
|
|
|
2009 Overlay & Pulverization
Project Complete
|
May, 2009
|
June, 2009
|
|
|
12600 South/3800 West Traffic Signal
(Riverton Hospital/Lowes)
Project Complete
|
January 2009
|
Spring 2009
|
|
|
11800 South/4000 West Intersection Improvement
Project Complete
|
April 2009
|
May 2009
|
|
|
13400 South Roadway Improvement Project
2700 West to 1700 West (Redwood Rd)
Project Complete
|
March, 2009
|
June, 2009
|
12600 South
Bangerter Highway
|
|
2009 Crack Seal Project (89 Streets)
Project Complete
|
April, 2009
|
May, 2009
|
|
|
13400 South Road Improvement Project
3600 West to Market Center Drive Project Complete |
September
2008 |
Spring 2009
|
3600 West
|
|
2009 Slurry Seal
Project Complete
|
May, 2009
|
June, 2009
|
|
|
13400 South Irrigation Project
2700 West to 1750 West
Project Complete
|
December 2008
|
February 2009
|
|
|
1300 West Sidewalk, 12400 South - 12467 South
Project Complete
|
|
|
|
|
13400 South Road Improvement Project
5200 West to Bangerter Highway Project Complete
|
|
|
|
|
12600 South Roadway and Sewer Reconstruction Project
4570 West to Bangerter Highway Project Complete
|
|
|
|
|
|
|
|
|