Riverton City
Road Construction Updates

Below is information on current and future road construction within the City.    

Project
Start Date
Completion Date
Alternate Routes
11800 So Riverton Improvement Projects, Phase 3
 
Three part project to include: the addition of curb/gutter/sidewalk across the frontages of developed properties; sidewalk, property, and storm drain tie-in’s, and intersection improvements at 3600 West and 11800 South.
 
See Purchasing Web Page for Tabulation Awards
Lane Reduction’s Expected
 
July 2010
Sept,  2010
 
RDA Beautification Project Redwood Road
 
Roadway Completed; Landscaping to be completed in July 2010
 
Project includes the addition of curb/gutter/sidewalk across the frontages of properties; storm drain tie-in’s; asphalt and property tie-ins; Extensive landscape beatification.
 
See Purchasing Web Page for Tabulation Awards
April, 2010
August, 2010
2700 West &
1300 West
Street Light Retrofit
 
Project Complete
May 2010
July 2010
 
Public Works Wash Bay
 
Project Complete
May 2010
June 2010
 
11800 (2240 West -Redwood) Roadway Improvement Project
 
Project Complete
March, 2010
July, 2010
 
Overlay (4 Streets)
 
Doreen, Chartwell, 1830 West, Brindie Way
 
Project Complete
 
June 2010
June 2010
 
Micro Surface (6 Areas)
 
Project Complete
 
May 2010
June 2010
 
Slurry Seal (6 Areas)
 
Project Complete
 
May 2010
June 2010
 
ADA Ramps- Doreen Drive & 1830 West
 
Project Complete
 
April 2010
May 2010
 
ADA Ramps- Chartwell Area & Brindy Way
 
Project Complete
 
April, 2010
May, 2010
 
2010 Crack Seal Project (Micro-surface, Slurry Seal, and Overlay Area’s)
 
Project Complete
 
April, 2010
April, 2010
 
 
 
 
 
11800 (2700-2240 West) Roadway Improvement Project
 
Project Complete
 
April, 2009
September, 2009
11400 So & 12600 So
1300 West Riverbend Roadway Improvement
 
Project Complete
July, 2009
August, 2009
 
 
2009 Overlay & Pulverization
 
Project Complete
May, 2009
June, 2009
 
12600 South/3800 West Traffic Signal
(Riverton Hospital/Lowes)
 
Project Complete 
January 2009
Spring 2009
 
11800 South/4000 West Intersection Improvement
 
Project Complete
April 2009
May 2009
 
 
13400 South Roadway Improvement Project
2700 West to 1700 West (Redwood Rd)
 
Project Complete
March, 2009
June, 2009
12600 South
Bangerter Highway
2009 Crack Seal Project (89 Streets)
 
Project Complete
 
April, 2009
May, 2009
 
13400 South Road Improvement Project
3600 West to Market Center Drive

Project Complete
September
2008
Spring 2009
 
3600 West
2009 Slurry Seal
 
Project Complete
 
May, 2009
June, 2009
 
13400 South Irrigation Project
2700 West to 1750 West
 
Project Complete
December 2008
February 2009
 
1300 West Sidewalk, 12400 South - 12467 South 
 
Project Complete
 
 
 
13400 South Road Improvement Project
5200 West to Bangerter Highway
 
Project Complete
 
 
 
12600 South Roadway and Sewer Reconstruction Project
4570 West to Bangerter Highway
 
Project Complete
 
 
 
 
 
 
 

 